Milestones

Milestone Template

Documents Template

WorkPackage 0

M1: Project internat review (M6)

M2: Project internat review (M12)

M3: Project internat review (M18)

M4: Project internat review (M24)

M5: Project internat review (M30)

M6: Project internat review (M36)

WorkPackage 1

M1: Network requirements (M3)

M2: Network scenarios and guidelines for testbed configuration (M6)

M3: Preliminary results on optimised network architecture (M18)

WorkPackage 2

M1: First indication on failure scenarios and resilience strategies (M6)

M2: First report on resilience interworking strategies in multilayer networks (M16)

WorkPackage 3

M1: Specification of functionality of the available planning and simulation tools (M9)

M2: Definition of network planning case studies (M18)

WorkPackage 4

M1: Functional description of an IP-based transport network

WorkPackage 5

M1: Specification of the core management functionality of the umbrella system (M9)

M2: Network level information model for the subsystem interfaces of the umbrella system (M12)

M3: Revised information model (M22)

WorkPackage 6

M1: OA&M specification for integreation of network elements in the testbed (M6)

M2: Definition of OA&M strategies for the testbed (M17)

WorkPackage 7

M1: Implementation of subsystem for IP-routers (M12)

M2: Testing of subsystems and umbrella management system for testbed (M25)

WorkPackage 8

M1: Testbed configurations: identification (M15)

WorkPackage 9

M1: Preliminary testbed subsystems tests performed (M15)

M2: Testbed pre-trials (M27)

M3: Final testbed integration (M30)

M4: Testbed experimental results (M34)